This addition in Brentwood’s Fountainhead neighborhood started with an existing concrete pad beside the house. The project photos follow the work through demolition, footing excavation, poured footers, block foundation walls, exterior wall protection and the new concrete slab.

Start with the existing concrete and the layout

The first photo shows marked concrete beside the house. The project scope called for concrete demolition and excavation for two additions. Removing the existing surface opens the area for the new foundation layout.

Marked concrete beside a Brentwood home before addition excavation
Existing concrete marked out before removal for the addition work.

Excavate the footing trenches

The next photo shows the trenches with reinforcement in place. Footings support the foundation walls, so their location, dimensions and reinforcing details come from the project plans. An addition needs to fit the existing house as well as the new layout.

Footing trenches and reinforcement at a Brentwood addition
Excavated footing trenches with reinforcement in place before the pour.

Footers for bearing walls poured in place

Concrete was poured into the excavated footing trenches to form the footers for the bearing walls. The block foundation walls were built on these footers. The slab came later, after the foundation walls and the work beneath the floor were in place.

Concrete placed in addition footing trenches in Brentwood
Poured-in-place concrete footers before the block bearing walls were built.

Waterproofing and foundation drainage

The next stage is easier to see before it is covered. The photo shows the exterior coating on the block wall and the drain rock beside it. Wall protection and drainage work together: the coating helps limit moisture reaching the masonry, while the drain rock and foundation drain provide a path for water to move away from the wall.

Exterior foundation coating and drain rock beside a Brentwood addition block wall
Exterior foundation coating and drain rock alongside the block wall, before backfilling.

The foundation drain and the downspout lines have different jobs. The foundation drain collects water around the below-grade foundation. Solid downspout lines carry roof runoff to a defined outlet. For more on those choices, see property drainage and water getting under a house.

The new concrete slab

With the block walls in place and the floor area prepared, the crew poured and finished the new slab. The October 2 photo shows the concrete being finished inside the foundation walls beside the existing house. It brings the photo sequence from the original pad through the new foundation and slab.

New concrete slab being finished inside the block foundation at a Brentwood addition
The new slab on pour day, with finishing work underway inside the block foundation walls.

What homeowners can take from this project

Concrete removal, excavation, foundation work and drainage need a coordinated scope. Agree on the layout, the water outlets and where excavated soil can go before starting. Access beside an existing house also affects the work sequence and restoration.

Our grading and site-shaping work connects the finished ground to the drainage plan. If the problem is existing ground settling rather than a new addition, our sinking-yard repair example explains why identifying the cause comes first.